Subject: 2013-06-21 Press Release - Olsen Road Watermain Upgrade
Immediate
Release
Construction Update – Friday, June 21,
2013 as of 2:00 pm
Upgrades to the Olsen Road Watermain will
begin on Monday June 24th. There will be traffic interruptions and no parking
along Olsen Road during construction, but the road will remain open. Water
service interruptions will be kept to a minimum and 48 hours notice provided.
This project is scheduled to be completed by July 15,
2013.
The upgrade includes installations of new
hydrants and service connections. This project is funded through Property Value
Tax Levies and the Small Community Investment Fund. The work is being completed
by David Stalker Excavating of Ladysmith B.C.
The project area has been identified as
culturally sensitive. An Archaeologist and cultural scanners will be onsite at
all times examining the soil for culturally significant artifacts. Significant
findings will be kept on site until a transportation permit is
issued.
Media Contact
Bob Schantz
Manager of Public Works and Building
Inspection
The District of Tofino
(T) 250 725-4212
This is cool!
ReplyDelete