Pages

Friday, October 28, 2011

Why Tofino Didn't Get The Sewer Grant in 2009

In response to many questions asked regarding my question at the All Candidates Meeting: Why Didn't Tofino get any grant money during the largest Infrastructure Grant Program in Canadian History ?
I didn't expect Perry Schmunk to have an answer to this but I did expect a better answer from Michael Tilitzky as he was on council at the time.Tilitzky gave a vague answer and didn't address the facts presented below from previous TofinoNews blog posts from 2010:


even more sewer grant stuff July 14,2010

from the sewer grant application:
"Phase 2 of the project will include Integrated Resource Management to generate heat and electricity from wastewater treatment,will consider anaerobic digestion of wet ,organic waste in combination with biosolids(to generate biodiesel/biogas) and will consider reduction/gasification of solid wastes (including digested biosolid residue and wood residue from logging and land clearing(hog fuel) to generate energy and heat."
"Phase 1 of this project will recover heat from a proposed sewer lift station and will use this heat to offset heating costs in proposed Fire Hall and RCMP public buildings. Solar hot water heating will be explored to offset some of the remaining energy costs. Although only considered in preliminary form at this time, the opportunity to generate energy from a future turbine installed in the outfall pipe of the proposed Sewage Treatment Plant (STP) will be considered together with opportunities to generate heat,biofuels and electricity from the Phase 2 of the project that will include design,construction and commissioning of the future STP."

posted by Ralph Tieleman at 12:56 PM 10

even more sewer grant info July 14,2010

From a letter from Don McKinnon (Tofino Public Works Superintendent)dated March 16, 2009 regarding the the sewer grant application: " I have,however not completed a construction cost estimate (yet) based on the alignment proposed in our Project # 23010 Feasibility Assessment (please refer to Appendix A of initial submission), and cannot complete it in time to meet the March 16,2009 deadline. We respectfully request that you factor our challenges into your evaluation criteria and do not penalize our community because we have staff time and budget challenges."

I guess these challenges were overcome with regards to the traffic roundabout that became a beautification project at the North Chesterman's Beach parking lot as the District of Tofino was successful in securing a grant for that project.

posted by Ralph Tieleman at 9:00 AM

more sewer grant info July 14,2010

from the Westerly News : "The utility corridor is directed through undeveloped land owned by the District of Tofino," MacKinnon said, "how the province interpreted we were building the corridor to access new development lands is beyond me, based on all the information placed into the grant application."
from the Sept.2008 Utility Corridor Feasibility Study:" Construction costs for that portion of the revised Arnet Road Utility Corridor through DL122,are anticipated to be paid for by the property owners.These costs will include the proposed intersection and highway widening at future Arnet Road and Campbell Street,the proposed Sewer Lift Station, the proposed Water Pump Station,the 200mm diameter watermain,the 200mm diameter Sewer Forcemain and the Arnet Road (Utility Corridor),all constructed as DCC projects.Following the construction,District of Tofino would then offer a DCC rebate for the incremental portion of the costs beyond the local requirement, as described in the Development Cost Charge Bylaw Amendment 2008.
from an obtained document "Project Benefits District of Tofino Sewage Treatment Phase 1-Arnet Road Utility Corridor" : page 2. "Facilitates future development of more than 100 ha or (sic) land presently inaccessible and undeveloped (Dl 114,117,118 and 121 ).
It should be noted that DL 121 is being considered for development by local First Nations.

posted by Ralph Tieleman at 7:37 AM 2 Comments
Tuesday, July 13, 2010
Sewer Grant information July 13,2010
Here's an excerpt from a July 8,2010 interview with the Tofino Public Works Superintendent as it appeared in the Westerly News:
"The utility corridor is directed through undeveloped land owned by the District of Tofino," MacKinnon said, "how the province interpreted we were building the corridor to access new development lands is beyond me, based on all the information placed into the grant application."
However documents obtained by TofinoNews show the proposed utility corridor passing through private lands;DL 122 !!

"Where the revised alignment of the Utility Corridor may terminate at Campbell Street is shown on attached Figure 7.This alignment shows a conceptual layout of turning lanes,acceleration lanes for southbound traffic, a left-turn lane for northbound traffic with sufficient area to accommodate an estimated 18 to 20 vehicles (130 lineal metres), all adjacent to DL122 frontage,which is currently at rezoning,OCP amendment and imminent subdivision stages." The attached figure 7 shows the utility corridor intersecting with Campbell Street over private lands just south of the ambulance station.
The original plan for the utility corridor had it connecting to Campbell Street by means of the existing Industrial Way.

I don't think anyone on Tofino Council took the time to read this grant application before it was submitted.Tofino Council was responsible for this failure.

No comments:

Post a Comment